Installation conditions of graphitization furnace

Oct 18,2024

Enray

Installation conditions of graphitization furnace-power 1. transformer capacity: transformer capacity shall be equipped according to the power of the equipment, and some margin shall be reserved; 2. Cable type: five-wire system (3 live wires +1 zero wire +1 ground wire) 3. Cross-sectional area: calculate current according to the power of the equipment, and then calculate the cross-sectional area of the cable 4. Material: BV or BVR multi-core flexible copper wire 5. Isolation switch: according to the power of the equipment, calculate the current and the size of the isolating switch. Note that domestic brands can only be used according to 70% of the quota current, while imported developed country brands can be used according to 90% of the quota current without leakage protection, otherwise they cannot be used.

graphitization furnaceInstallation conditions

1Power

1. The capacity of the transformer: according to the power of the equipment to be equipped with transformer capacity, and to leave some margin;

2. Cable model: five-wire system (3root line of fire 1Root zero line 1Root ground wire)

3. Cross-sectional area: calculate the current according to the power of the equipment, and then calculate the cross-sectional area of the cable

4. Material: AdoptBVorBVRMulti-core soft copper wire

5. Isolating switch: Calculate the current according to the power of the equipment and calculate the size of the isolating switch. Note that domestic brands can only use the amount of current70%Use, imported developed country brands can be in accordance with the amount of current.90%Do not use with leakage protection, otherwise it will not work

6. Length: according to the actual distance from the transformer or power cabinet to the equipment

2Cooling water

1. Calculate the matching cooling tower or refrigerator according to the flow rate and heat dissipation of the equipment;

2. Cooling tower or refrigerator water tank tap water supplement port (soft water is recommended, the water quality in the north is hard and scaling is serious, and the equipment will be blocked for a long time)

3. Power failure and water cut-off standby power supply: generator, generator power matching with cooling tower or chiller power, standby water: tap water pipe connected with equipment cooling pipe

3Compressed air: provide 0.4-0.8Mpa compressed air interface

4Protective gas: argon nitrogen